Main tasks in this project were: static and dynamic analysis of the structure, connection calculations, 3D modeling in Tekla for production and preparing installation drawings.
Our 5-person team consisted of structural and detailing engineers and finished the project in 2.5 months, so the first steel structures from factory in Tallinn (Estonia) were delivered at site 4 months after initial design was agreed with the client.